On April 9, the groundbreaking ceremony for Elk’s new production facility in Schrems took place. Pictured from left to right: Wolfgang Ecker, President of the Lower Austrian Chamber of Commerce (WKNÖ); Renate Giller-Schilk, District Governor of Gmünd; David Süß, Mayor of Schrems; Stefan Graf, Master Builder; Johanna Mikl-Leitner, Governor of Lower Austria; Dr. Matthias Calice, CEO of the Elk Kampa Group; Markus Wieser, President of the Lower Austrian Chamber of Labor (AKNÖ); and Markus Schandl, Authorized Representative of Elk Schrems © Alex Foret, Elk GmbH

elk

1,500 prefabricated houses starting in 2028

Article by Philipp Matzku (translated by Eva Guzely) | 16.04.2026 - 12:02

Elk is investing €60 million in the expansion of its production capacity at its headquarters in Schrems in the Waldviertel. A new production hall with 16,100 m² of floor space and 1,400 m² of office and social areas is being built on a site that is nearly 40,500 m² big. Construction is to be completed in the second quarter of 2027, and production is to start in early 2028. With the new production hall, Elk will further expand and consolidate the in-house manufacturing of wall, ceiling and roof elements.

“In the new hall, we will further standardize the production process and automate it with suitable machinery wherever it makes sense,” Markus Schandl, authorized signatory, plant manager, and project manager for the production expansion at Elk, emphasizes. The new hall will house a nesting system, a station for the assembly of timber frames, new joinery machines, and a storage area. Furthermore, an additional €10 to €15 million is earmarked for restructuring the existing production hall, but concrete plans are still being developed. Some of the older machinery will be moved to the new production hall. The existing hall will remain in operation after 2028.

In addition, the construction of a 1-MW photovoltaic system is planned in Schrems, as is the switch from gas to district heating when it comes to heating supply.

Currently, around 20,000 m³ of wood are processed annually at the Schrems site. Elk processes an average of 145 m³ of wood for a single-family home.

Expansion and strengthening of the market position

Elk_FranzWall_COO.jpg

Franz Wall, COO of the Elk Kampa Group © Philipp Matzku

Elk prefabricated houses are manufactured by the Elk Kampa Group at two production sites in Austria and Germany. In 2025, 840 prefabricated houses were produced in Schrems/AT and 250 in FreiwaldeDE in the German state of Brandenburg. In 2024, production in Schrems totaled 630 prefabricated houses, representing an increase of 33%. With the expansion of production capacity to 1,500 houses a year, this corresponds to a 79% increase within two years.

In Schrems, production currently takes place in two shifts. Even after the capacity increase, the 1,500 houses are to be manufactured in a two-shift system. Elk employs approximately 1,000 people at the Schrems site. The commissioning of the new production facility is expected to create around 150 additional jobs.

In 2025, the Elk Kampa Group recorded cumulative sales of around €300 million, of which €210 million were generated by Elk and €90 million by Kampa. For 2026, Franz Wall, COO of the Elk Kampa Group, expects an increase to a total of €400 million, with Elk contributing a projected €320 million. This corresponds to growth of around one third for the group and of slightly more than 50% for Elk. Germany is the main target market for Elk prefabricated houses. The order backlog amounts to €500 million until the end of the first half of 2027.

“We are among the market leaders in prefabricated timber construction. With this investment in our production capacities, we aim to achieve further growth, build ecologically and sustainably, and secure our significant role in this segment over the long term,” Dr. Matthias Calice, CEO of the Elk Kampa Group, comments. “We believe in this location. Schrems remains Elk’s heart,” Wall adds.